Disneyland Paris is preparing for an extensive refurbishment of Animagique Theater, with two permits now approved covering the demolition of three backstage buildings and significant technical upgrades to the theater.
Meanwhile, Mickey and the Magician is scheduled to end its current run on January 10, 2027, marking the beginning of an extended hiatus. No reopening date has been announced so far.
The upcoming works could also coincide with changes to the production itself. Following the opening of World of Frozen, the Frozen sequence may no longer feature in the show when it eventually returns. However, no changes to the show’s content have been officially confirmed, and the future of other sequences, including The Lion King, remains unknown.
Three backstage buildings to be demolished
A demolition permit was approved on November 10, 2026, covering three buildings located behind Animagique Theater.
The three structures, some of which are prefabricated buildings, are scheduled for complete demolition. Their combined surface area represents approximately 315 m², distributed as follows:
- Building 1: 235 m²
- Building 2: 35 m²
- Building 3: 45 m²
A further permit could be submitted in the coming weeks for the construction of new backstage facilities on the site of the demolished buildings. This possibility remains unconfirmed at this stage.
Major technical refurbishment of the theater
A substantial prior declaration (Déclaration Préalable) was approved on October 30, 2026, detailing several technical interventions, particularly on the theater’s rooftop above the indoor queue area.
The approved plans include several categories of work:
Roof and safety equipment
- Creation and installation of two translucent skylights (skydomes) above the indoor queue.
- Installation and replacement of the existing rooftop guardrails along the same area.
Heating, ventilation and air conditioning
- Removal of the existing air-handling units (CTA) and associated ductwork.
- Supply and installation of new air-handling units.
- Installation of new galvanized steel supply and return-air ducts, connected to the existing ventilation grilles.
Roof waterproofing
- Refurbishment of the existing roof waterproofing.
- Installation of new metal flashings (couvertines), matching the existing design.
The planning documents accompanying the application provide further details of the proposed rooftop installations and the building’s elevations.
What about the theater’s exterior façade?
The approved plans do not indicate any modifications to the theater’s main exterior façade.
The current façade refurbishment is also nearing completion. The left-hand section of the banner has been reinstalled in a more robust version, while the right-hand section is still missing.
However, its supporting framework is already in place, suggesting that the remaining section is still expected to be reinstalled.

When will the works begin?
The demolition and technical refurbishment works, as well as any potential subsequent backstage construction, are expected to take place during the show’s hiatus.
With Mickey and the Magician scheduled to end on January 10, 2027, work is therefore not expected to begin before January 11, 2027.
Several months of works are anticipated, although no detailed construction schedule or reopening date has been announced.
A major technical project behind the scenes
The two approved permits already reveal the extent of the upcoming refurbishment at Animagique Theater. Beyond the visible improvements, the project includes substantial interventions to the building’s ventilation, rooftop equipment and waterproofing, alongside the demolition of three backstage structures.
With the possibility of new backstage facilities still to be explored, further developments could follow behind the scenes at Disneyland Paris.